GESU PARISH
BUILDING PROGRAM  - SCHEME I


The data gathered from meetings and analysis of conditions has contributed to an understanding of current and anticipated needs. This Scheme is the minimal approach for the Parish Center, identifying the least amount of work anticipated to achieve functioning facility. The division of space shall remain except as indicated. In addition the Church will receive modifications. The following is the Building Program that has evolved for Scheme I.

Facilities for a Parish Center:

Add handicapped ramp on exterior

New entry to building

Current dining room to become general office area

Enhance the reception function, provide for security

Provide new handicapped toilet

Existing kitchen to become break room

Provide for resource/library space

Demo some bathrooms on second floor

Provide sprinkler system in basement

New electrical power system

New lighting & emergency lighting systems

New exit signage & fire alarm

New heating, ventilating & air conditioning systems

New data/communication systems

Patch and repair existing surfaces

Provide new interior finishes

Enhance acoustics

Re-roof flat roofs

Secure storage – fire and waterproof

General storage

Modifications to the Church

Provide new-handicapped accessible elevator connecting McAuley Hall to all floor levels.

Provide new entry at the piazza.

Provide ramp from the main Church floor to the Sanctuary level.

Provide new full immersion baptismal font incorporating the existing font Location to be determined.

Freshen finishes in the Church; new paint, clean stone, renew wood.


 
 

Scheme I Renderings:

Scheme I First Plan
Scheme I Second Plan
Scheme I Site
Scheme I

 

 
     
  GESU PARISH
BUILDING PROGRAM  - SCHEME II

The data gathered from meetings and analysis of conditions has contributed to an understanding of current and anticipated needs. This scheme is for the entire renovation of the existing Parish Center. Space allocation, mechanical, electrical and structural systems will be all new. The following is the Building Program under considerations for Scheme II.

Facilities for a Parish Center (Former Rectory):

Facilities for a Parish Center (Former Rectory):

3 priest’s offices – first floor

3 counseling rooms – first floor

1 office for office coordinator/pastor’s secretary – first floor

1 office business manager – first/second floor

1 office for assistant business manager – second floor

2-3 front office people – first floor

1 receptionist – first floor

1 office for development director – second floor

1 office for pastoral ministry – first/second floor

Meeting/multi-purpose room, 30 to 40 people – first floor

Kitchenette/staff break room – first floor

Room for office equipment – first floor

Secure storage – fire and waterproof

General storage

Office for RCIA coordinator (preferred in the Reg. Ed Ctr.)

Modifications to the Church

Provide new-handicapped accessible elevator connecting McAuley Hall to all floor levels.

Provide new entry at the piazza.

Provide ramp from the main Church floor to the Sanctuary level.

Provide new full immersion baptismal font incorporating the existing font. Location to be determined.

Freshen finishes in the Church; new paint, clean stone, renew wood

Maintenance

Find additional space for materials and equipment used outdoors.

Maintenance office.

 
 


Scheme II Renderings:

Scheme II Elevations

Scheme II First Plan
Scheme II Second Plan
Scheme II Site
Scheme II

 
     
  GESU PARISH
BUILDING PROGRAM  - SCHEME III

The data gathered from meetings and analysis of conditions has contributed to an understanding of current and anticipated needs. This scheme razes the existing rectory building and has a new building with expanded functions built in its place. The Building Program for Scheme III is as follows:

NEW PARISH HALL & ADMINISTRATIVE CENTER

Facilities for Administrative Center

1 Pastor’s office

2 Priest’s offices

3 counseling rooms

1 office for office coordinator/pastor’s secretary

1 office business manager

1 office for assistant business manager

2-3 front office people

NEW PARISH HALL & ADMINISTRATIVE CENTER

1 receptionist

1 office for development director

1 office for pastoral ministry

1 resource/library space

Meeting/multi-purpose room, 30 to 40 people

Kitchenette/staff break room

Room for office equipment

Secure storage – fire and waterproof

General storage

Office for RCIA coordinator (in the Reg. Ed Ctr.)

Meeting Hall    

Main assembly space (375 per @ 15sf ea)

Commercial kitchen

Storage (tables& chairs)

Lobby/gathering space                                                

Maintenance

Provide space for materials and equipment used outdoors.

Maintenance office.

CHURCH

Modifications to the Church

Provide ramp from the main Church floor to the Sanctuary level.

Provide new full immersion baptismal font incorporating the existing font. Location to be determined.

Freshen finishes in the Church; new paint, clean stone, renew wood

 

 
 

Scheme III Renderings:

Scheme III Elevations
Scheme III First Plan First Plan
Scheme III Second Plan
Scheme III Site
Scheme III A
Scheme III B

 
     
 

Other Renderings:

Scheme IV Church Plan
Scheme IV Enlarged Church
Scheme IV Elevator
Scheme V Elevator
Scheme V Elevator Plan
Scheme V Front
Scheme V Ramp